Project One

 

Drying a Historic Building After a Fire

 

 

 

DETAILS

 

Grade II listed church which was damaged by fire in 2007.

 

The practice was engaged to advise on the affect the water introduced to the building would have on the existing fabric of the building and how this would affect the proposed repair and refurbishment.

 

Moisture probes were installed to all parts of the building to establish the level of trapped moisture within the fabric, this allowed targeted drying measures to the wettest areas.

 

Tests were undertaken to all moisture probes on a monthly basis to track the rate of drying and allowed the construction programme to be modified accordingly so there would be no problems of trapped moisture after the completion of the works.

 

newhay_1.jpgNewhay_2.jpgPicture_3.jpg

Fire Service damping down

Fire and water damage internally

CONTACT  Tel  0161 436 4079  mobile  07880527313  

Building Surveyor Manchester , Historic Building Survey, Quinquennial Inspection, Non destructive timber survey, listed building surveyor , listed buildings, timber surveyor, Building Surveyor Cheshire

Building Surveyor Manchester , Historic Building Survey, Quinquennial Inspection, Non destructive timber survey, listed building surveyor , listed buildings, timber surveyor, Building Surveyor Cheshire  

Building Surveyor Manchester , Historic Building Survey, Quinquennial Inspection, Non destructive timber survey, listed building surveyor , listed buildings, timber surveyor, Building Surveyor Cheshire  

 

MCABE_2.png